Bear Mountain Parkway Completion Project

6 February 2018

The City of Langford started construction of the Bear Mountain Parkway Completion Project in October 2016. This project will see Bear Mountain Parkway completed from the intersection of Leigh Road at McCallum Road (the upper end of the Leigh Road Interchange) continuing approximately 3.3km uphill to meet with the existing Bear Mountain Parkway located at the existing roundabout at Country Club Way.

Windley Contracting has been awarded the construction contract. The anticipated opening date is Wednesday April 4, 2018. The City is waiting to finish some paving and is also waiting for the power supply to power up the streetlights from BC Hydro. We will update our website as more information becomes available.

The road is not open to the public during construction.

Click here to view the Completion Project Map.

Click here to view photos of the project. 